County supervisors this week affirmed support for plans by Dominion Energy to build a transmission line up through south ...
The closure will run from 7 a.m. to 7 p.m. on July 16, continuing through July 20. If work is delayed, the closure could run ...
UI wants to rebuild just over eight miles of transmission lines and install new steel monopoles from the Southport section of Fairfield to the Congress Street substation near downtown Bridgeport ...
FAIRFIELD — The National Trust for Historic Preservation has joined the campaign against a controversial United Illuminating plan to upgrade transmission lines ahead of an important hearing ...
They include inspections of all transmission structures and equipment including, but not limited to, monopoles, steel towers, wood poles, conductors (wires), insulators and other equipment.
This week, Dominion will begin installing vibratory caisson foundations needed to support monopole transmission structures.
During an evidentiary hearing Thursday before the State Siting Council, Shawn Crosbie, UI's projects unit manager for transmission lines, refused to consider revising the design of the monopole ...
ITC will be conducting aerial patrols of the high-voltage transmission structures and lines in Michigan from approximately Sept. 11 – Oct. 11, weather permitting.